A project fee needs a delivery plan behind it
A signed architectural fee can look generous until the firm separates consultant commitments, design revisions, and the work still required during later phases. Review the fee against a current phase plan, not only against invoices already issued. A project that has billed well may still have too little budget left to finish responsibly.
Use the actual contracted phases and services. Name what the architect performs, what consultants perform, what the owner provides, and what requires a separate authorization. Keep assumptions about meetings, submissions, revisions, and construction-period involvement with the fee plan so later changes can be explained.
Separate the gross fee from the firm's own delivery budget
AIA's fee guidance describes developing effort by task and phase and distinguishing consultant allocations from the fee available for architectural work. Use that distinction to avoid comparing the whole client fee with only the firm's payroll. Consultant spending may be a substantial part of delivery even when the invoice passes through your office.
For a hypothetical $120,000 client fee, assume committed consultant fees total $30,000. That leaves $90,000 before the firm's own delivery costs and any other relevant costs. If forecast internal delivery cost is $60,000, the resulting $30,000 is a defined project contribution before omitted overhead or other items, not automatically net profit.
| Project layer | Keep visible | Question for the reviewer |
|---|---|---|
| Client agreement | Fee, scope, and approved changes | What has the client actually bought? |
| Consultant commitments | Agreed fees and remaining services | What is already committed? |
| Internal phase plan | Hours, roles, and cost assumptions | What effort remains? |
| Billing schedule | Milestones and approval conditions | When may the firm invoice? |
| Collections | Invoices, credits, and receipts | What is still unpaid? |
References: American Institute of Architects: Setting project fees
Review each phase using remaining effort
Compare the phase budget with actual time and the current estimate to finish. Ask the project lead to describe unfinished tasks, outstanding decisions, and expected consultant coordination. A statement that a phase is nearly complete is less useful than a list of the work needed for the next submission.
Suppose a phase has a hypothetical $25,000 internal delivery budget, $22,000 of cost already incurred, and $9,000 of work still expected. Its forecast cost is $31,000, creating a $6,000 overrun. The fact that another phase has not yet started does not erase that result. Reassess the whole project, but preserve the explanation for the phase that changed.
Avoid moving time to a later phase solely to make the current one match its budget. Correct genuine coding errors with a reason and approval. If the scope or delivery plan has changed, issue a revised forecast with an effective date. The original estimate remains useful for learning where the fee assumptions were wrong.
Track consultant commitments before invoices arrive
Maintain a consultant schedule showing original fee, approved additions, services completed, amounts billed, and estimated remaining work. A low accounts-payable balance may simply mean the consultant has not invoiced. Ask for progress information where material rather than treating the absence of a bill as unused project budget.
Separate owner-approved additional services from consultant work the firm has authorized at its own risk. If a consultant expands scope before the client accepts a fee change, record the commitment and the unresolved recovery. Do not count a hoped-for client approval as if it were already a signed addition to the project.
Keep phase progress and invoicing conditions distinct
AIA describes several charging arrangements, including hours worked, milestone payments, and phase-based progress billing. Those are commercial terms that affect invoice timing. The percentage of budget spent does not automatically establish that a contractual milestone has been met or decide the firm's financial-reporting revenue treatment.
Retain the submission or acceptance evidence needed for the actual agreement. If the firm has completed work but a client decision blocks a milestone, show that condition in the billing forecast. If invoices are outstanding, identify whether the issue is ordinary payment timing, missing approval, scope disagreement, or a service concern.
References: American Institute of Architects: Charging for architectural services
Turn the review into a specific project decision
Ask whether the remaining fee and resources can support the current scope. The response may be a revised staffing plan, a documented additional-service proposal, a consultant discussion, or an explicit acceptance of lower contribution. Keep the commercial decision separate from any accounting estimate the controller needs to review.
At project close, preserve the original phase plan, approved changes, actual effort, consultant costs, and final collections. Compare projects with similar scope and delivery conditions when setting the next fee. A difficult approval process or repeated owner revision has more estimating value when it is described specifically than when it disappears into a single unfavorable project percentage.
Sources
Requirements and product details can change. Check the linked guidance for the facts that apply to your situation.
Related reading
Need help with this work?
General information, not personalized accounting, tax, legal, or investment advice. Have the appropriate qualified professional review decisions that depend on your circumstances.