Document when a project asset becomes available for use

Collect commissioning, acceptance, and operating evidence before transferring an asset from construction in progress and starting its approved accounting schedule.

By Institution3 minute readPublished View sources
In this guide

Ask when the asset could perform its intended job

The final supplier invoice may arrive before or after an asset is ready to operate. Ask the project owner for the date the asset reached the location and condition needed for its intended use, supported by commissioning, acceptance, or operating evidence. The accountant should assess that date under the company's framework before moving costs out of construction in progress.

For Australian reporting, AASB 116 paragraph 55 starts depreciation when an asset is available for use. Its wording focuses on readiness for intended operation. Other reporting bases need their own assessment; the operational handoff should preserve the facts rather than selecting a date solely because a budget closed or a purchase order was fully paid.

References: Australian Accounting Standards Board: AASB 116, current compilation for periods beginning before 2027

Separate completed components from unfinished work

A larger project can contain components that become ready at different times. Identify the parts, their purposes, and their dependencies. Ask the accountant whether separate components require separate accounting. Do not assume that the whole project must remain in one unfinished balance until the final minor task ends, or that one working component proves the entire system is ready.

For an illustrative facility project, production equipment begins its intended operation in June while a separate storage installation remains unfinished until August. Retain the acceptance evidence and costs for each. The example does not prescribe the unit of account; it shows why the reviewer needs component-level facts before approving dates and transfers.

Reconcile the cost population at the transfer date

List invoices, approved estimates for work performed, credits, and other project costs included in the recorded balance. Identify amounts still awaiting invoices and amounts relating to future work. Have the accountant determine which costs qualify for the asset and which need another treatment. A project cost report is not automatically a financial-reporting capitalization schedule.

Record the proposed transfer by asset or component, including account destinations and supporting references. Reconcile the total transferred plus the remaining construction balance to the original schedule. Keep unresolved costs visible. Do not allocate a residual to the completed asset simply because the project manager wants the construction account cleared.

Give the depreciation preparer the necessary facts

Provide the approved start date, asset description, location, responsible owner, cost, and accounting assumptions. Obtain useful life, residual value, and method approval from the appropriate reviewer. The operating owner can supply expected use and maintenance facts, while the accountant determines the accounting estimate. Tax depreciation decisions are a separate specialist task.

Check whether the accounting system will calculate a partial period, a full period, or another convention from the approved inputs. Verify the actual application behavior before relying on the first journal. If the asset became ready before the current close, ask the accountant to assess the affected periods rather than choosing the current date to avoid reviewing history.

Resolve trailing invoices without reopening the whole project blindly

Link late invoices to the original project component and compare them with estimates already recorded. Identify duplication, price changes, and genuinely new work. Have the accountant approve any adjustment to the asset or other account, including the period effect. Keep the original transfer evidence so later amounts do not erase the readiness decision.

Retain a completion packet containing the approved transfer, readiness evidence, cost reconciliation, and first depreciation check. Leave unfinished components on a separately owned schedule with their next expected milestone. The next close can then review actual remaining work instead of carrying a completed project in construction in progress because one document has not arrived.

Sources

Requirements and product details can change. Check the linked guidance for the facts that apply to your situation.

Related reading

Need help with this work?

General information, not personalized accounting, tax, legal, or investment advice. Have the appropriate qualified professional review decisions that depend on your circumstances.