Commission a production time study that finance can use in costing

Specify the operations, observations, time definitions and approval evidence a production time-study provider must deliver before its results enter product costs.

By Institution6 minute readPublished View sources
In this guide

Define the costing decision the study must support

A time study should answer a specific operating question before its results enter a product-cost model. The business may need to replace an unsupported routing estimate, understand a changed process or distinguish setup work from repetitive production. Commission the evidence for that decision rather than buy a spreadsheet of unexplained minutes.

The International Labour Organization describes work study as a detailed examination of how a job is performed. For a costing assignment, identify the approved process, products, site and operations to be examined, with the responsible technical and workforce owners involved. The study should observe or evaluate an agreed method, not silently redesign work to meet a desired cost target.

State the intended use in the engagement. A routing-cost input, a capacity estimate and an employee performance measure have different implications. Approval to develop a costing estimate should not be treated as approval for every possible later use of the observations.

References: International Labour Organization: Work-study scope

Separate the time concepts in the requested deliverable

Ask the provider to distinguish observed time, any adjusted or normal time, allowances and the final standard it proposes. The Institute of Industrial and Systems Engineers' terminology distinguishes raw observed time from time adjusted for the relevant method and allowances. A column headed time should not conceal which stage it represents.

Require an explanation of every adjustment, its basis and who must approve it. If the provider uses a performance rating, allowance or other convention, finance should be able to see its effect without being asked to endorse the technical judgment itself. Preserve the original observations alongside the proposed result.

Separate elapsed time, hands-on labor and machine occupancy where they differ. One operator may attend several machines, and a machine may run while the operator performs another task. Adding every elapsed interval as labor cost can double-count time that overlaps.

Identify setup, running, inspection, handling and other relevant elements individually. Microsoft’s standard-cost guidance illustrates why this matters: setup time can apply per lot while run time applies per produced unit. A single average that blends them changes when batch size changes and may be unsuitable as a stable routing input.

References: Institute of Industrial and Systems Engineers: Work-measurement terms; Microsoft Learn: Routing time and lot-size inputs to standard cost

Sample the actual operating population

Define which products, configurations, machines, shifts and conditions the observations represent. A study of one easy product on a recently maintained machine should not automatically become the standard for a broader family. Require the provider to state exclusions and the evidence supporting any grouping.

Include startup, normal operation and relevant interruptions according to the approved study design. The specialist should decide how observations are classified and whether more data is needed. Finance should not remove slow cycles merely because they increase the average, or retain every unusual event as though it were routine.

Record the method and conditions with each observation batch. A changed tool, material specification or work sequence can make later observations incomparable with earlier ones. Preserve the change rather than combine all measurements into a larger sample that no longer describes one process.

Agree how staff will understand the purpose and how observation records will be handled. The engagement should respect the company's workforce policies and technical requirements. Collect only the personal information needed for the authorized study and avoid exposing individual records in a general costing workbook unnecessarily.

Check a small calculation with the denominator visible

Assume a hypothetical study records twenty comparable cycles totaling 36 minutes of observed work. The simple arithmetic mean is 1.8 minutes per observed cycle. That number alone does not establish a standard time; the provider still needs to explain representativeness, the defined cycle and any approved adjustments.

Suppose, separately, the qualified reviewers approve a normal-time input of two minutes for the example. If an allowance is defined as 15% of normal time, the resulting standard is 2.30 minutes: two multiplied by 1.15. The difference from the original observations should remain documented rather than disappear into the final figure.

If a different method instead defines the allowance as 15% of the final standard time, the calculation is two divided by 0.85, or approximately 2.35 minutes. Both examples use the label 15%, but the denominator differs. Ask the provider to state the definition before finance reproduces the formula.

These figures are invented to illustrate the calculation review. They are not recommended production standards, allowances or performance ratings. The responsible specialists must establish appropriate assumptions for the actual work and requirements.

Translate the accepted time into the cost model carefully

Record the unit in which the routing expects time: seconds, minutes or hours, per item, per batch or another defined quantity. A study in minutes per ten units should not be entered as minutes per single unit. Retain the conversion in the handoff rather than rely on the implementer's memory.

Using the hypothetical 2.30-minute standard and an illustrative approved labor rate of $30 per hour, the direct labor component is $1.15 per unit. That is 2.30 divided by sixty, multiplied by $30. It excludes machine cost, setup and other elements unless the approved rate and scope explicitly include them.

Check whether the costing rate already contains an allowance or indirect component that the time input also includes. The provider and accountant should explain the intended combination. A reasonable time estimate and a reasonable hourly rate can still overstate cost if they account for the same effect twice.

Treat setup separately where the process requires it. The study should supply the supported fixed preparation event and its duration, while the cost model uses an approved lot assumption. Changing the lot denominator is a different decision from measuring how long the preparation takes.

Accept evidence that the company can maintain

Require a defined deliverable containing the operation description, observations, exclusions, calculations, proposed standards, limitations and approvals. The company should be able to reproduce a sample result and understand why it applies to the selected product population.

Ask for a clear distinction between observed findings and recommendations to change the process. A proposed future method may require engineering, safety or workforce approval before it can become the basis of current cost. Do not install its projected time as an achieved standard simply because the recommendation appears in the same report.

Include a handoff to the people maintaining routing data. They should know which values change when a product, machine or method changes and which require a new study. A consultant's result becomes stale if nobody owns the conditions that made it valid.

Keep the prior routing estimate and the approved replacement. When reported unit cost changes, management needs to know whether the change reflects better evidence, a new method or an actual operating improvement. Those explanations should not be collapsed into one favorable efficiency percentage.

Validate the first costing use without repeating the entire study

Select a representative production order and trace the accepted time inputs into its estimate. Confirm units, resource rates, batch treatment and the relevant version. The test should show that the system uses the study as intended, rather than reperforming every observation.

Compare a later appropriate run with the accepted assumptions and investigate material differences with the operating owner. One unusual run does not automatically invalidate the study, but a persistent mismatch may show that the method or population changed.

A completed engagement leaves finance with explainable inputs and leaves production with ownership of their technical meaning. The useful result is a cost estimate connected to defined work and evidence, with a clear route for revision when that work changes.

Sources

Requirements and product details can change. Check the linked guidance for the facts that apply to your situation.