Give every job its own numbers
A contractor can appear profitable overall while losing money on a long-running project. Assign labor, materials, subcontractors, equipment use, and other direct costs to a job as they arise. Keep general company overhead separate so the job-cost report answers what a specific contract is earning.
Give field staff an easy way to record the job number when they submit hours or receipts. Asking an accountant to reconstruct job costs from card descriptions at month-end usually leaves too much to guess.
Compare the original estimate with the work still to do
At each review, show the approved contract value, approved changes, costs to date, estimated cost to complete, billed amount, and cash received. If material prices or labor hours rise, revise the cost-to-complete estimate rather than showing last month's margin as though nothing changed.
A change order belongs in the forecast when it is properly supported. Track requested, approved, and invoiced changes separately so a disputed request is not treated as guaranteed revenue.
Billing ahead and working ahead are different problems
Progress invoices do not always match the value of work performed at the same date. Depending on the accounting method and contract, the company may need contract asset or liability balances for work done but not billed, or amounts billed before they were earned.
Reconcile the billing schedule to the job ledger and the contract terms. Cash can be strong temporarily because of a deposit even when a project has a cost overrun, or weak because an otherwise profitable milestone has not yet been billed.
Keep retainage visible
Suppose a contractor invoices $80,000 for approved work and the customer retains 10 percent. The full invoice is $80,000, but only $72,000 is currently payable and $8,000 is held back under the contract. Track that $8,000 separately, with the conditions and expected timing of release.
If the contractor also withholds retainage from subcontractors, track that amount as a separate obligation. Do not offset customer retainage and subcontractor retainage just because they occur on the same project.
Protect payroll and subcontractor records
Allocate field hours to jobs and, where applicable, the classifications needed for payroll, insurance, or certified payroll reporting. Collect subcontractor tax documentation and insurance records where required by law or contract. Check the actual worker-classification and reporting obligations rather than assuming every person paid on an invoice is an independent contractor.
Equipment purchase, depreciation, repairs, and internal equipment usage may affect job costs in different ways. Use a consistent allocation policy and keep supporting schedules.
Close open jobs with questions, not just totals
At month-end, reconcile bank accounts, subcontractor payables, customer receivables, retainage schedules, and billed or unbilled work. Then look for jobs with negative margin trends, costs booked to the wrong project, disputed changes, or unusual billing gaps.
Keep book reporting and tax reporting requirements distinct. Construction contract accounting and tax methods can depend on contract terms, size, and applicable rules; ask the preparer which schedules they need before year-end.
Mistakes to avoid
Booking all costs to overhead and learning only at year end which jobs lost money. Recording retainage as collectible cash. Paying subcontractors without a W-9 or insurance certificate. Failing to track change orders until they are approved, when the work is already done. And mixing personal and business purchases at the supply house.
Frequently asked questions
What is work in progress?
The difference between what you have billed on a job and the revenue you have earned on it, based on how much of the work is complete. It appears on the balance sheet as an asset or a liability.
Should retainage be on the balance sheet?
Yes. Retainage you are owed is a receivable, and retainage you hold back from subcontractors is a payable.
How do I handle change orders?
Track each one by job with its status. Record revenue when it is approved or when you have a reasonable basis to expect payment, and ask your CPA how your method treats unapproved work.
Sources
Requirements and product details can change. Check the linked guidance for the facts that apply to your situation.
Related reading
Need help with this work?
General information, not personalized accounting, tax, legal, or investment advice. Have the appropriate qualified professional review decisions that depend on your circumstances.