Construction work in progress: the monthly review behind project reports

Connect contract value, approved changes, costs, remaining work, billing, and retainage before relying on a project’s reported margin.

By Institution2 minute readPublished View sources
In this guide

Reconcile the contract position

Start with signed contract value and approved changes. Identify pending claims or change orders separately. Management may expect to recover them, but that expectation needs review before it enters accounting or a cash forecast.

Use one project identifier across purchasing, payroll, billing, and reporting. A cost assigned to the wrong job can distort two projects while the company total still looks correct.

Review costs incurred and remaining

Reconcile job costs to payroll, supplier bills, equipment, subcontractors, and other direct records. Check invoices received after cutoff for work performed in the period.

Ask the project owner for a dated cost-to-complete estimate. Explain changes in labor, materials, scope, schedule, and rework. The accountant should assess the reporting method and any loss or estimate treatment under the applicable framework.

Separate billing from performance

Show billed amounts, cash received, retainage, and the relevant accounting revenue or contract balances. A progress invoice is not by itself evidence of the accounting completion measure.

For illustration, a project billed $200,000 with $20,000 retained has a different collection schedule from one paid in full, even if both have the same approved billing. Track the release conditions and expected date.

Review exceptions with operations

Discuss unapproved changes, disputed bills, stalled milestones, missing receiving records, and unusual margin movements. Give each issue a project owner and accounting reviewer where needed.

Do not offset one project's unexplained balance against another. Keep project-specific evidence so a consolidated number can still be traced.

Keep a dated review package

Retain contract values, changes, cost detail, remaining-cost estimates, billings, collections, retainage, and the review conclusion. Preserve revisions rather than overwriting the prior month's assumptions.

Use recurring discrepancies to improve purchasing and project reporting inputs. A useful WIP review tells management which jobs need action and gives accounting an explained basis for the monthly figures.

Sources

Requirements and product details can change. Check the linked guidance for the facts that apply to your situation.

Related reading

Need help with this work?

General information, not personalized accounting, tax, legal, or investment advice. Have the appropriate qualified professional review decisions that depend on your circumstances.